Monitoring of the Coastal Safety Embankment (NCICD) of Muara Baru and Kali Adem, North Jakarta

Monitoring of the Coastal Safety Embankment (NCICD) of Muara Baru and Kali Adem, North Jakarta

Thursday (16/09) The Phase 4 Package 2 Coastal Security Project was one of the locations visited by the Coordinating Minister for Maritime Affairs and Investment of Indonesia Luhut Binsar Panjaitan. Also attending were Minister of PUPR Basuki Hadimuljono, Minister of Agrarian and Spatial Planning Sofyan Djalil, Minister of Maritime Affairs and Fisheries Sakti Wahyu Trenggono, Governor of DKI Anies Baswedan and welcomed by Director of Operation II Waskita Bambang Rianto.

This presentation on the Beach Safeguard Project Phase 4 Package 2 was delivered directly by the Director General of Water Resources of PUPR, Jarot Widyoko.

The construction period for this project is 850 days and the completion target is December 2022.

With this project, it is hoped that it will support coastal security around DKI Jakarta.